No Damages for Delay Provision Saves Contractor's Delay Claim from Notice of Claim Provision

In Huen New York, Inc. v. Board of Education Clinton Central School District, Supreme Court, County of Oneida, Index No. CA2005-001680, Greenberg, Trager & Herbst, LLP represented Huen New York, Inc. ("Huen"), the prime contractor for the electrical work on a large new construction project for the School District, which was to be completed in two phases ("Project"). Huen's work on the Project was scheduled to be completed in January 2003, but was actually completed in September 2004. Thereafter, Huen brought a claim against the School District for delay damages.