Innovative and cost-effective solutions for clients in the construction and real estate industry. 212-688-1900

February 2015 Archives

No Damages for Delay Clause Found to be Enforceable, Despite 22 Month Project Delay

Although it is settled law that a no-damages-for-delay clause which exculpates a contractor from liability for damages resulting from delays in the performance of the work is generally enforceable, various courts have applied the exceptions enunciated by the Court of Appeals in Corinno Civetta Constr. Corp. v. City of New York, 67 NY2d 297 (1986) in denying dismissal motions based upon the clause. Those exceptions are:

Email Us
Greenberg, Trager & Herbst, LLP Nearly a century of construction law excellence
Back to top